DIRFT III
The Daventry International Rail Freight Terminal (DIRFT) project included a 4 span portal frame with internal office, MSCP, rail canopy, training facility and VMU.
Billington Structures supplied, fabricated and erected over 4,000 tonnes of construction steelwork including metal decking, Easi-edge and pre-cast concrete stairs on this prestigious project.
Work included installation of curved roof trusses to the amenities hub and installation of a large trussed link bridge between the MSCP and the main warehouse.
Main Contractor
Buckingham Group Contracting Ltd
Engineer
RPS
Architect
SGP Stephen George Partnership
Value
£6,200,000